The Carlyle Update

Project completed September 2018

The Carlyle Update

Ground floor slab and below levels have all been completed with Level 1 formwork, well under way.

Posted: Sunday 4 February 2018

Osprey Update

Bulk excavation nearing completion, which has us on track to pour slab on ground by mid-February. The forming of our first suspended slab will follow, with the target  being the end of February.

Posted: Sunday 4 February 2018

Osprey Update

Demolition is now 50% complete, the project is well underway. Not long now till we are in the ground.

Posted: Friday 1 September 2017

The Carlyle Update

With the in ground works making head way, not long before the first portion of the slab on ground is poured.

Posted: Tuesday 15 August 2017

The Carlyle Update

Site completely Demolished and cleared with shoring now commencing.

Posted: Monday 15 May 2017

OSPREY at 5 MOORAMBA ROAD, DEE WHY – DA APPROVED

OSPREY is Dee Why’s latest development to be DA Approved.

Posted: Monday 27 February 2017

PHOENIX COMPLETED

70-72 Amy Street, Campsie is now completed and all the owners who have settle have moved into the development.

Posted: Thursday 15 December 2016

PHOENIX RESIDENTS TO MOVE IN

We are in the final stages of completing the construction of 30 units at 70 Amy Street, Campsie and are expecting the Occupation Certificate within the next couple of weeks.

This will allow purchasers who have settled to be able to move into their units prior to Christmas.

Posted: Wednesday 7 December 2016

THE CARLYLE NEARS CONSTRUCTION PHASE

The first stages of demolition of 699–701 Pittwater Road, Dee Why, is underway to begin the construction of 162 units over 15 levels.

We are very excited for the start of another successful project.

Posted: Monday 5 December 2016